Ad Code

Responsive Advertisement

Management Civil Engg. [MSBTE] I scheme {Unit :- 2}

 Unit:-2

1. Following are the physical resources

(a) Man (b) Machine

(c) Material (d) All

2. This is concept in manpower planning.

(a) Matching needs of customer with business (b) Matching quality with quantity

(c)Matching human needs with job needs (d) All are wrong

3. Supervisor is

(a) Engineer (b) Manager

(c)Team leader

4. Who plan capacity of machine?

(d) All the above

(b) Supervisor

(d) Quality Inspector

(a) Operator

() CEO

5. Cycle time is concerned with

(a) Automobile (b) Operator's work

(c) Machine and Process (d) Time office

Management 2.14 Planning and Organizing at Supervisory Level

6. What are the advantages of prescribing standard forms in planning?

(a) Systematic planning

() Factual information

(b) Standardization

(d) All the above

7. Which information is not necessary in Raw material acceptance form?

(a) Quantity

()Cycle time

8. Which information is not necessary in job description?

(b) None of material

(d) Inspected by

(a) Job name (b) Operations

(c) Cycle time

9. Machine load chart is not doing this.

(a) Check the feasibility of production programmes

(b) Assist the efficient planning

(d) All

(C) Training of operators

(d) Fixing of reliable delivery promises

10. is an instrument of management used in planning, programming and control of business

financial activity.

(a) Inspection (b) Budget

() Quality

is a financial statement prepared and approved prior to a defined period of time

(a) Audit

(d) Audit

1.

(b) Control charts

(c) Budget (d) Order of payment

12. means forecasting and preplanning with reference to finance.

(a) Budget

(c) Control

(b) Audit

(d) Inspection

13. Following is not the information needed for planning at Supervisory level.

(a) Number of jobs to be done (b) Time expectation

()Profile margin

14. Following is not done planning by supervisor.

(d) Sequence of operations

(a) Selection of machines (b) Assigning workers

(c) Allocate time for operations (d) Marketing of products

15. What are the important informations to supervisor while planning?

(a) Quantity of jobs

(c) Quality standards

16. While selecting machines, what kind of information is not necessary to supervisor?

(b) Delivery time

(d) All

(a) Total machines (b) Cycle time

() Operations required (d) Maintenance standards

17. While allotting work to workers what information is not important?

(a) Qualification

()Abilities

(b) Skills

(d) Specialities

18. In planning

1. Rescheduling must not be avoided

2. f needed, do rescheduling

(a) Only 1 correct (b) Only 2 correct

(C)Bothc orrect (d) Both wrong

Management 2.15 Planning and Organizing at Supervisory Lovel

19. While planning which parameters does supervisor observe.

(a) Manpower

(C) Oversight

20. () Supervisor makes short-term planning.

(i) Managers make long-term planning.

(b) Schedule

(d) A

(Gii) Supervisor do scheduling of daily activities

(a) Only 1 is correct

(c)Only 1 and 2 correct

21. Securing raw material from stores is the responsibility of

(b) Only 2 is correct

(d) All correct

(a) Supervisor (b) Line manager

(C)Purchase manager

22. Supervisor is

(a) Completely

(d) Materials manager

focussed in planning.

(b) Internally

(c) Externally (d) None of the above

23. Supervisor plans budget on . expenses and manager plans budget on . expenses.

(a) Small, Large

()External, Internal

24. What is the upward correct chronology?

(b) Large, Small

(d) None of the above

1. Worker, 2. Foreman, 3. Supervisor, 4. Manager, 5. Shift incharge, 6. Helper

(a) 1-6-3-5-2-4 (b) 6-1-3-2-5-4

(c) 6-1-2-3-5-4 (d) 1-6-3-2-4-5

25. Safe working condition is the responsibility of .

1. Worker, 2. Supplier, 3. Supervisor, 4. Manager, 5. Factory Head, Customer

(a) 2, 3,4, 6 (b) 1, 3, 5, 6

() 1, 2, 3, 4 (d) 1,3, 4, 5

26. ) Planning of material is responsibility of supervisor.

Gi) Planning of manpower is the responsibility of HR manager and not of supervisor

(a) Only 1 is correct (b) Only 2 is correct

(c) Both are correct (d) Both are wrong

27. Following qualities are not required in organizing skills of supervisor.

(a) Planning (b) Decision making

(c) Financial knowledge (d)Time management

28. When there is change in technology

(a) Plan fails (b) Plan has to be modified

()Plan must be rescheduled (d) All of the above

29. When emergency situation comes.

(a) Continue previous Planning (b) Change the situation

() Change the plan (d) None of the above

30. Planning by supervisor is

1. Interdependent process 2. A continuous process

3. Integration of various activities 4. Looking into past

(a) 1 and 2 correct (b) 2 and 3 correct

() 1, 2 and 3 correct (d) 2,3 and 4 correct

Management 2.16 Planning and Organizing at Supervisory Level

31. Supervisor can delegate his task to_

1. Foreman 2. Worker

3. Colleague 4. Senior manager

(a) 1 and 2 only

(c) 2 and 4 only

32. Good relations in a group helps to.

(b) 1 and 3 only

(d) 1,2 and 3

(a)Increase comfort level (b) Closeness

(c)Friendships (d) Only (a) is more correct

33. Supervisor organizes

1. Man, 2. Machine, 3. Material, 4. Money, 5. Work orders.

(a) Only 1, 2,5 (b) Only 1, 3, 5

() Only 1, 2, 3 (d) All

34. Supervisor fails to plan if_

(a) He is not dynamic

(C)He is not popular

(b) He is not educated

(d)He is not senior


Answers

1. (d) 2. (_ 3. (d)4. (b)
13.(c)
5. (c) 6. (d)
16.(d)_
26.(a)
7. (a) 8. (d)9. ()10. (b)
11.c 12.a) 14.(d)15. (d)_ 17.(a) 18.() 0.(d)
27.c) 28.(d)
(d)
21.(a) 22.(b) 23.(a) 24.(c) 25.(d) 29.(c) 30.(c)
31.(d) 32.(d) 33.(c) 34.(a)

Post a Comment

0 Comments

Ad Code

Responsive Advertisement