Q.1) Technical sanction is given after the administrative approval
a) True
b) False
Q.2) What is the year of Maharashtra act no VI
a) 2008
b) 2009
c) 2010
d) 2007
Q.3) Minimum experience of structural engineer-2(SE-2)
a) 4 year
b) 3 year
c) 5 year
d) 1 year
Q.4) Which survey should be performed by every structural engineer before repair of the
structure
a) Visual survey
b) Distress survey
c) Non-destructive test
d) None
Q.5) From which survey we know the exact information about the time required for the
completion project
a) Distress survey
b) Detailed survey
c) Visual survey
d) None
Q.6) Detailed inspection includes
a) Removal of material of distress area and surrounding
b) Material type and approximate quantity
c) Man power required
d) All of them
Q.7) ........cost which cannot be avoided at the time of repair
a) Hidden
b) Convert
c) Indirect
d) None
Q.8) The duration of curing has been considered as per the type of ....used for repair
a) Cement
b) Mortar
c) Material
d) None
Q.9) State the first step of the structural audit
a) Visual inspection
b) NDT
c) Collection of general information of building
d) Core testing
Q.10) General information of building collected from....
a) Owner
b) Contractor
c) Site engineer
d) Labour
Q.11) Types of auditing are
a) Structural
b) Safety and budgeting
c) Statutory
d) All of these
Q.12) Objectives of the auditing structure is
a) Health monitoring
b) Save the life
c) Checking the condition of the structure
d) All of these
Q.13) what is an important tool in the distress survey?
a) Detailed inspection
b) Visual inspection
c) Chemical attack
d) None
Q.14) Non-destructive test used in the structural audit is
a) Rebound hammer test
b) Ultrasonic pulse velocity test
c) Impact echo method
d) All of these
Q.15) Non-destructive test is used to measure
a) Surface hardness
b) Capacity of concrete
c) Both
d) None
Q.16) What is the goal of budget management
a) To control project costs within the approved budget
b) To deliver the project within the expected time
c) Both a & b
d) None
Q.17) In budget estimation the mantra goes
a) Money is Time
b) Time is Money
c) Both
d) None
Q.18) The main factors to be considered while budget estimation are
a) Manpower
b) Material
c) Equipment
d) All of these
Q.19) Why budget estimation required?
a) To identify project risk
b) To prevent the unnecessary cost of the project
c) To know the overall return on investment
d) All of these
Q.20) Purpose of structural audit
a) To identify project risk
b) To prevent the unnecessary cost of the project
c) To know the overall return on investment
d) All of these
Q.21) When a structural audit is done?
a) 15 to 30 years
b) 10 to 20 years
c) 15 to 25 years
d) None
Q.22) Why structural audit is important?
a) Understand the condition of the existing structure
b) Distress level of the existing building
c) Its premises safe and have no risk
d) all of these
Q.23) The need for a structural audit is for maintenance and repair of existing structures
whose age is more than.....
a) 15 years
b) 20 years
c) 10 years
d) None
Q.24) The project budget is the total sum of money allocated for the particular purpose of
the project for the specific period of time
a) True
b) False
Q.25) Budget estimate is used to:
a) Control expenditure
b) Benefit-cost ratio
c) Funding planning
d) All of these
Q.26) While preparing distress maps, propping plan, load transfer which inspection will
play an important role?
a) Visual
b) Detailed
c) Both
d) None
Q.27) Detailed inspection includes
a) Man power
b) Any special tool
c) Material type
d) all of these
Q.28) The problem found to be non-availability of plans and drawing of structure in this
case engineer has to...
a) Redraw
b) Found
c) None
Q.29) Any settlement in foundation is works under ........inspection
a) Distress
b) Detailed
c) Visual
d) None
Q.30) Which chemical test provided in the structural audit
a) Carbonation test
b) Chloride test
c) Sulphate test
d) All of these